Umatilla Chemical Agent Disposal Facility weekly project update - February 10, 2011

The Umatilla Chemical Agent Disposal Facility processed 15 TCs over the weekend, pushing the project over the midway point of the mustard ton container campaign.

It is the 13th and final individual munitions disposal campaign for the plant. Through Sunday, the Metal Parts Furnace had processed 1,325 donor TCs. The halfway mark was 1,318 TCs.

The HD mustard disposal campaign started in June 2009. It is projected to finish late this year, a little more than seven years after the first munition was destroyed in the fall of 2004.